What changed on this project, newest first. The Product Owner keeps this updated: if a story, a point value or the scope looks different from last week, the reason is written here.

September 23, 2026

  • Production information removed from the product. A teammate asked how we would measure what a system produces: without monitoring hardware we can only guess, and a guess is not worth showing.
  • Upgrades stay simple: the site shows what your budget buys today next to the cost of the full system. No staged plans, because a budget now is not a promise about next month.
  • Backlog rebuilt around how the team learns. Stories are now pages and lists (the stuff teams can build right now); every add, edit and remove is its own separate story; and the calculation engines wait in the backlog, written without specific numbers or methods, until the class covers that material.
  • Sir's list is in: new list modules for clients, suppliers, installers, technicians, subscription packages, maintenance plans, products and services, plus a My system page where customers record solar equipment they already own.
  • Every story now has a Simplified tab: plain words explaining exactly what to build, so nobody has to guess what a story means.
  • Stories can be moved back a stage without releasing them (team and sprint stay attached).
  • Upgrades now ask for three things: what you already own, the space you have available, and your budget. The recommendation fits all three.
  • The product page was rewritten to explain the finished product: by I4 this is a working solar business platform, and the current lists are phase one of it.

September 22, 2026

  • Direction locked in by the Product Owner: the product is the calculator core, plus a supplier directory with referral requests, referral tracking and simulated commissions and listing fees, plus loans and a staged growth plan. The loans and growth plan come straight from the original project brief.
  • Backlog review: 25 stories, 55 points. Easier stories were re-pointed down (register and log in is now 1 point, since the class had most of it built already). Real engine work keeps its weight at 3 to 5 points.
  • Stories no longer carry a sprint. A story gets assigned to an iteration only when a team pulls it, the way sprint planning is supposed to work.
  • Wording across all stories: “electrical equipment” instead of “appliances”, because the product serves businesses and that is the language of the project brief. Stories are also technology neutral now: no “page” or “click” wording, so they can be built for any interface.
  • Sprint goal saving on team pages: clearer guidance about who can save, and regression tests now cover saving a goal and editing an existing one.
  • New guide pages for the team: the product direction in plain words, the calculations explained, and the break-proofing list.
  • Coverage audit: the whole backlog was checked against the product direction, independently and twice. Three promises had no story behind them, so three stories were added: 1.2 Property profile (sizing that respects your actual roof), 6.2 Bill comparison (before and after solar, side by side) and 9.3 Results with assumptions (every number shows the assumptions behind it). The backlog is now 28 stories, 61 points.

September 21, 2026

  • Team pages: member sub-roles added. A Scrum Master can set each member's working role: Developer, Business Analyst, Designer, Implementer or Tester. These are the roles that rotate each iteration; Product Owner and Scrum Master stay at the account level.
  • Jabar added to Team 3, taking the class to 32 people across 6 teams.

September 20, 2026

  • Project Charter draft circulated to the team: 6 Scrum teams, 32 people, one shared product backlog, completion November 11, 2026.
  • Scope baseline in the charter reflects the team's direction choice at the time (calculator plus catalogue only). Superseded on September 22 when the sponsor asked for wider scope; see the September 22 entry.

September 16 to 17, 2026

  • ScrumSync tracker launched for the class with 7 accounts (1 Product Owner, 6 Scrum Masters), one shared product backlog, sprint goal tracking and a full activity log.
  • Iteration 1 backlog reviewed story by story with the Product Owner and loaded: 15 stories covering the landing pages, accounts, equipment inventory, catalogue and the core calculation engines.